What happens after the NCE is submitted ?

- NCE serves to inform us of the intended earthworks.
- For Low Pressure (LP) gas pipes, you will be given a letter on the requirements within 7 days.
- For HV cables and Medium Pressure/Gas Transmission Pipes, ESP will contact you within 1 to 2 working days to arrange for a site visit.
- An officer will meet up with you to find out how the high voltage cables or medium pressure / transmission gas pipes will be affected, and to give useful precautionary measures to take cable damage arising from the proposed earthworks.
- The ESP officers will check to ensure that all cable and gas pipe positions are properly pegged and trial holes are properly made. (Please note that NCE is required for digging trial holes as it is considered "earthworks" under Section 2 of the Electricity Act and the Gas Act).
- A letter of requirements will be faxed and mailed to you and you have to comply with these during the course of the earthworks.
- You may then proceed to commence earthworks at the end of the 7 days notification period or a later date, as stated in your NCE, after you have complied with all the recommendations given by your LCDW and SP PowerGrid.
- We will continue to work closely with the contractor and visit the sites regularly to ensure incident-free completion.