- NCE must be submitted for earthworks in the vicinity of high voltage cables and all gas pipes.
- The NCE must be submitted to SP PowerAssets and/or PowerGas at least 7 calendar days prior to the commencement of any earthworks.
- No earthworks are to be carried out within the 7 calendar days after an NCE is submitted.
- It is an offence under the Electricity Act and the Gas Act not to submit a NCE before carrying out earthworks in the vicinity of high voltage underground electricity cables and/or gas pipes, or commencing earthworks short of the 7 calendar days as stated in the notice.
- Anyone found guilty of these offences is liable to be prosecuted and if convicted, to a fine up to a maximum of $100,000 or imprisonment of up to 5 years or both.